Uttar Pradesh, INDIA

Expertise

CAPACITY

75 MW

 

Expertise

REACH OF ELECTRICITY SUPPLY

109,312 PEOPLE

Expertise

CO2 REDUCTION

41,200 TONNES P.A.

Landkarte Portfolioreport Web Uttar Pradesh I

PROJECT DETAILS

Project Special Purpose Vehicle (SPV) Talettutayi Solar Projects Five Private Limited („Karnataka II“)
Location Budaun District, State of Uttar Pradesh, India
Technical Specifications
  • Grid connection: To an existing Bilsi substation, 5 km away
  • Fixed tilt mounting structure, using polycrystalline solar PV technology
Reach of Electricity Supply 109,312 people
New permanent jobs TBC
Supplier/Manufacturer TBC
General Contractor (EPC) TBC
Operations & Maintenance TBC
Lender's Engineer TBC
Electricity Offtake Counterparty Power Purchase Agreement with Uttar Pradesh Power Corporation Ltd. (UPPCL)
Credit Rating Electricity
Offtake Counterparty
ICRA: C
Specifications of the Power Purchase
Agreement (PPA)
Statutorily guaranteed Tariff fixed rate INR 3.21 (USD 0.05) per kWh, allocated through a reverse auction bidding process. The rate has been set and approved for 25 years.
Status Land acquisition is under progress. The plant is expected to achieve commercial operations in March 2020.

Status: 30.06.2019