Karnataka II
12. March 2019
ISLASOL I A
20. February 2020

Uttar Pradesh I

Uttar Pradesh I in Budaun District in the state of Uttar Pradesh is a 75-megawatt solar power plant commissioned in January 2021. It was developed by Delhi-based SolarArise India Projects Pvt Ltd, an innovative operator of grid-connected solar power projects in India. Since fall 2018, ThomasLloyd has been the largest shareholder with a significant stake in SolarArise.

Project site

PROJECT SITE

Uttar Pradesh, India

CO2 reduction

CO2 REDUCTION

103,684 tonnes p.a.

Reach of electricity supply

REACH OF ELECTRICITY SUPPLY

93,295 people

Capacity

CAPACITY

75 MW

Project Videos

 
 

Impressions of the project

Project details

Project Special Purpose Vehicle (SPV) Talettutayi Solar Projects Five Private Limited (“Uttar Pradesh I”)
Location Baramay Khera Village, Budaun District, State of Uttar Pradesh, India
Coordinates: 28.06240° N, 79.02576° E
Technical Specifications Project site: 894,356 m²
Solar irradiation at project site: 1,824.2 kWh/m²/year (SolarGIS)
Grid connection: To an 132 kV existing Bilsi UPPTCL substation, 5 km away
Fixed tilt mounting structure, using mono PERC solar PV technology
192,000 modules of rating 390Wp
Reach of Electricity Supply 93,295 people
New permanent jobs 55 in the plant
Supplier/Manufacturer Solar Modules: JA Solar (China)
Solar Inverters: Sungrow (China)
String Inverter: Sungrow (China)
Inverter Transformer: Raychem RPG (India)
Mounting Systems: Purshotam Profiles Pvt. Ltd. (India)
Control Panels: Technocrafts Switchgears Pvt. Ltd. (India)
HT Cables: KEI Industries (India)
LT Cables: KEI Industries (India)
String Cable: Siechem Technologies (India)
General Contractor (EPC) Jakson Limited
Operations & Maintenance Jakson Limited (5 years)
Lender’s Engineer PFC Consulting Limited
Electricity Offtake Counterparty Grid Connection Agreement with Uttar Pradesh Power Transmission Corporation Limited (UPPTCL). Power Purchase Agreement with Uttar Pradesh Power Corporation Ltd. (UPPCL).
Credit Rating Electricity Offtake Counterparty ICRA: C
Specifications of the Power Purchase Agreement (PPA) Statutorily guaranteed Tariff fixed rate INR 3.21 (USD 0.05) per kWh, allocated through a reverse auction bidding process. The rate has been set and approved for 25 years by the Uttar Pradesh Electricity Regulation Commission.
Status In full operation since January 2021.

Status: 30/06/2021

Thomaslloyd is a Signatory to the Principles for Responsible Investment (PRI)

and other Key Responsible Investment Initiatives

ThomasLloyd is committed to investing responsibly. We believe that the integration of material environmental, social and governance (ESG) factors into our investment process is a core part of our fiduciary duty to act in the best interests of our clients and their beneficiaries. To formally incorporate and systematically integrate ESG factors therefore in this process, we have developed a Socially Responsible Investment Policy, Methodology and Framework.


Find out more